780-Project GMPP Infrastructure Pipeline

Commitment: Maintain and deliver a pipeline of 780 major infrastructure projects through the Government Major Projects Portfolio (GMPP), overseen by NISTA.

Owner: HMT / NISTA / individual departmental SROs

Target date: Ongoing programme management

Metric: Project delivery ratings (Green/Amber/Red); total whole-life costs; properties protected; delivery against approved scope.

Status: at-risk

What the GMPP is

The Government Major Projects Portfolio (GMPP) is the register of the UK government’s highest-value and highest-risk infrastructure projects. NISTA (National Infrastructure and Service Transformation Authority) reviews all GMPP projects and publishes annual data on their delivery confidence ratings.

780 projects with a total whole-life cost of approximately £790bn are in the current GMPP.

Current delivery confidence (NISTA Annual Report 2024)

RatingProjectsDescription
GreenMinorityOn track
AmberMajoritySome concern
Red31Significant concern; £198bn whole-life cost

The 31 red-rated projects with £198bn in whole-life costs represent the core of the delivery-confidence-fiscal-ambition tension: the government projects £725bn investment but £198bn of the pipeline is already at significant delivery risk.

Key context

  • MOD has the largest departmental portfolio (47 projects)
  • Red-rated project types include defence procurement, digital transformation, transport, and some environmental schemes
  • The IS data correction (industrial strategy investment figure revised from £100bn to £72.33bn) also affects GMPP figures

Delivery history

  • [2023] NISTA established from Infrastructure and Projects Authority (IPA)
  • [2024] NISTA Annual Report: 27 red-rated projects
  • [2025] Annual update: 31 red-rated projects — deterioration over 12 months; whole-life costs £198bn